Boeing announced an updated schedule for its all-new 787 Dreamliner program that moves the commercial jet’s first flight into the second quarter of 2009 and first delivery into the first quarter of 2010. The new schedule reflects the impact of disruption caused by the recent Machinists’ strike along with the requirement to replace certain fasteners in early production airplanes. Prior to the strike that halted much of the company’s commercial airplane work from early September into November, the 787 was to make its first flight late in the fourth quarter of 2008. First delivery was slated for the third quarter of 2009.
Boeing is evaluating the specific impact of this delay on customer delivery dates and will provide customers with updated schedules once completed. The company is also determining any financial impact from this schedule change and will incorporate that into updated financial and overall airplane delivery guidance that will be released at a later date.